Paul Smart - Tue Mar 14 12:58:10 UTC 2017 Tue Mar 14 12:58:10 UTC 2017
I want to link task3 to have as predecessors both task1 and task2. That is task 3 has two predecessors. I can enter two predecesssors into task3's information but it does not form the second link and disappears from task3.
Any help would be useful
Ralf Banens - Mon Mar 13 21:35:59 UTC 2017 Mon Mar 13 21:35:59 UTC 2017
Hello,
I am a new user of planner software and have a question.
When i have a task of 2 weeks. The first week resource A does this task. In the second week resource B finish the task. Can i plan this in 1 task? Seems a lot of work to make a sub task divided in 2 tasks.  ... 
Lee Martínez - Mon Mar 13 18:10:34 UTC 2017 Mon Mar 13 18:10:34 UTC 2017
Hi
I'm totally new at this.
I've just downloaded the GanttProject 2.8.3 but cannot do it run.
Could someone help me? I need to know how to make it live.
Regards and thank you!!!!!!!!!!!!!!!!
Mark C. Walton - Mon Mar 13 14:39:42 UTC 2017 Mon Mar 13 14:39:42 UTC 2017

Can't verify e-mail


When I made my first post here it prompted me to verify my e-mail. When I click to link I received, I get an error:

Invalid verification token. Please try again or contact GanttProject team.  ... 
Mark C. Walton - Mon Mar 13 14:33:54 UTC 2017 Mon Mar 13 14:33:54 UTC 2017

Problem exporting to MPX


I just started using GanttProject (and was very happy to see it exists).

My issue is that I have an MPP given to me by someone else created in MS Project 2016.  ... 
Dmitry Barashev - Sat Mar 11 21:45:48 UTC 2017 Sat Mar 11 21:45:48 UTC 2017
from email

Is there any video tutorial which shows how an excel file has to be set up and imported into ganttproject ?
Andrea Marra - Fri Mar 10 11:14:53 UTC 2017 Fri Mar 10 11:14:53 UTC 2017
Hi,
while I use GANTT it would be great if I was not able to assign a task to a resource if the resource itself has on vacation. I mean, is it possible to introduce a bind that prevent from add a resource to a task if the resource is out of work or has scheduled to go on holiday? Is it feasible  ... 
Anh Thu Vo - Wed Mar 08 11:37:13 UTC 2017 Wed Mar 08 11:37:13 UTC 2017
How to get the successor?

Hi Dmitry,

I can get the predecessor with the method
...task.getDependenciesAsDependee()... on the class DependencyTableModel.java

but how can I get the successor? Can you please give me some information.

Thanks a lots.
Laurent Gaignon - Wed Mar 08 07:45:43 UTC 2017 Wed Mar 08 07:45:43 UTC 2017

Where is the ical import gone ?


Hi !
I actually use GanttProject for years in my projects. These are often during along years and i used the ical import to have calendars out of 2017 (2020 at the moment). So do I import calendar in GP using ical format...
Since 2.8.  ... 
Kim Vervink - Mon Mar 06 12:31:41 UTC 2017 Mon Mar 06 12:31:41 UTC 2017

Collapsible lines



Hello, I am pretty new to ganttproject but it looks great (and a lot easier than having to manually make this in Excel).

However I didn't see what manipulation I need to do to make subtasks which I can then hide or show.  ... 