Peter Wheal - Thu Feb 02 11:06:22 UTC 2017 Thu Feb 02 11:06:22 UTC 2017
Can I enter just tasks with durations and dependencies but no dates. This will enable me to set out the logic of my project
2 answers  
Dmitry Barashev - Fri Feb 03 17:53:20 UTC 2017 Fri Feb 03 17:53:20 UTC 2017
Is this question different from the one which you already asked? https://forum.ganttproject.biz/view/20170131164837_let6emqqaefve3le495cf514#3
Peter Wheal - Sat Feb 04 20:25:25 UTC 2017 Sat Feb 04 20:25:25 UTC 2017
Yes - apologies- I thought my first post had failed to send. I have now made a logic diagram by doing what Dmitri advise - putting all tasks to the same date.
Thanks
P