Hello,
I am a new user of planner software and have a question.
When i have a task of 2 weeks. The first week resource A does this task. In the second week resource B finish the task. Can i plan this in 1 task? Seems a lot of work to make a sub task divided in 2 tasks.
Is it possibel to set a date for the resource for a specific task? This way i can plan more resources for 1 task.
3 answers  
Dmitry Barashev - Mon Mar 13 22:11:14 UTC 2017 Mon Mar 13 22:11:14 UTC 2017
No, sorry.