Al Rone - Thu Aug 10 10:22:40 UTC 2017 Thu Aug 10 10:22:40 UTC 2017
Finish no Later Than vs. Deadline

Which of these tools should I rather use?

Scenario: My activity = collecting registration forms.I should have them all collected by 30.July, over a duration of 2 weeks that is --> so, rather say Finish no later than or make a deadline for the 30.July?
Duration: collecting all registration forms make take 2 weeks, but perhaps also only 3 days if everyone responds quickly.

And how long should i schedule the duration; the max. duration time of 2 weeks?

Thanks for your suggestions