Delay column issues.

Hi just downloaded this software, brilliant bit of kit.

I am a construction manager and want to allow drying times for certain processes before the next can begin. I assumed the delay column in the predecessors would do this but when i enter a value it does not adjust the start date. Could someone please shed some light.

Thanks in advance